Schedule

The project began in December 2012 and runs for two years.

Workpackage summary

Work package Title Lead partner Status
WP1 Management and Coordination, Outreach, Communication and Promotion NOC with support from SatOC Ongoing
WP2 Case Study Scientific Analysis Plan NOC

Completed July 2013

WP3 Development of Project Technical Specification CATDS Completed July 2013
WP4 Case Study Data Set Collection SatOC Completed Jan  2014
WP5 Case Study System Implementation, Product Development and Validation NOC Ongoing
WP6 Case Study Scientific Analysis CATDS Ongoing
WP7 Project Final Workshop, Scientific Roadmap and Project Closeout UKMO Workshop planning ongoing

Gantt Chart

Gantt PDF